Good work to everyone involved!
-bawolff On 2013-01-22 6:53 PM, "Ct Woo" ctwoo@wikimedia.org wrote:
All,
The switchover work is done.
The site was was available to readers throughout the migration work though it was in read-only mode for about 32 minutes, when Asher and Mark had to migrate the database masters over from Tampa to Ashburn.
We will cancel the reminding maintenance windows.
Thank you all for your patience and understanding.
Regards, CT Woo
On Sat, Jan 19, 2013 at 10:57 AM, Ct Woo ctwoo@wikimedia.org wrote:
All,
We will be proceeding with the datacenter switchover plan this coming Tuesday (Jan 22, 2013), unless we discover some unexpected and insurmountable issues in our tests between now and then.
During the 8-hour migration window on the 22nd, 23rd and 24th (from 17:00 UTC to 01:00 UTC hours / 9am to 5pm PST), there would be times (lasting about 30 minutes) where the site would be set to "read-only" mode, to facilitate master database switchovers from one datacenter to another. While the site should be available to readers, no new contents could be created, edited or uploaded.
We are aware of the inconvenience and we have put together plans to minimize such annoyances, e.g., automating much of the procedures, mitigating known risks, and performing tests to identify issues prior to deployment. Given the scale and complexity of this migration, we do
realize
not all operational impact is predictable. Some users could experience intermittent site unavailability and/or performance issues unfortunately.
You can follow the migration on chat.freenode.net<
(and not irc.freenode.org as mentioned in previous email) in the #wikimedia-operations channel.
Thanks, CT Woo
---------- Forwarded message ---------- From: Ct Woo ctwoo@wikimedia.org Date: Fri, Jan 11, 2013 at 12:07 PM Subject: Update on Ashburn data center switchover / migration – target date is week of 1/22/13 To: Wikimedia developers wikitech-l@lists.wikimedia.org, Development and Operations Engineers engineering@lists.wikimedia.org
All,
The Migration team is in the last lap on completing the remaining tasks
to
ready our software stack and Ashburn infrastructure for the big switchover day.
Per my last update,<
http://lists.wikimedia.org/pipermail/wikitech-l/2012-October/063668.html%3E
with the Fundraising activity behind us now, the team has scheduled the
*week
of 22nd January*, 2013 to perform the switchover. We are going to block a 8-hour migration window on the *22nd, 23rd and 24**th*. During those periods, *17:00 UTC to 01:00 UTC hours (9am to 5pm PST*), there will be intermittent blackouts and they will be treated as 'planned' outages.
You
can follow the migration on irc.freenode.org in the
#wikimedia-operations
channel.
The team is putting the finishing touches to the last few tasks and we will make the final Go/No decision on 18th Jan, 2013. An update will send out then. For those interested in tracking the progress, the meeting
notes
are captured on this wikitech page<
http://wikitech.wikimedia.org/view/Eqiad_Migration_Planning#Improving_Switch...
.
*Please note that we will be restricting code deployment during that week, allowing only emergency and critical ones only.*
Thanks.
CT Woo
Wikitech-l mailing list Wikitech-l@lists.wikimedia.org https://lists.wikimedia.org/mailman/listinfo/wikitech-l