Hi Dan,
I understand the goals here but the resource requirements surprise me:
"The proposer of this project estimates that the following resources are the minimum required to achieve this goal:
* 2 FTE iOS engineers * 2 FTE Android engineers * 1.5 FTE user-experience designers * 1 FTE product manager * 0.5 FTE scrum master * 1 FTE QA tester"
Why are (7 FTEs * 40 hours * 13 weeks = 3,640 labor hours) required to achieve what appears to be a simple goal?
Thanks (:
Pine On Mar 9, 2015 7:09 PM, "Dan Garry" dgarry@wikimedia.org wrote:
Breaking news! Product manager puts in project proposal for Q4 priorities! Read all about it!
https://www.mediawiki.org/wiki/Talk:Wikimedia_Engineering/2014-15_Goals/Q4#I...
Dan
-- Dan Garry Associate Product Manager, Mobile Apps Wikimedia Foundation