Greetings,
The analytics engineering team is now using ScrumBugs to manage and track it's commitments for every Sprint (2 week iterations).
Our current sprint started Thursday June 26 and ends Tuesday July 8th. You can see the Stories (features) and bugs we are presently working on: http://sb.wmflabs.org/t/analytics-developers/2014-06-26/
Note, the third pie chart "Story User" shows the beneficiaries of the features being implemented.
Hi,
On Tue, Jul 01, 2014 at 09:16:26AM -0700, Kevin Leduc wrote:
Our current sprint started Thursday June 26 and ends Tuesday July 8th. [...] http://sb.wmflabs.org/t/analytics-developers/2014-06-26/
Thanks Kevin!
But as the items on that page might (and already did) change during the sprint, let me also add the teams commitment from Thursday's sprint planning as static table inline:
Commited Features:
+--------+--------+--------------+-------------------------------------------+ | Bug Nr | Points | Component | Bug Summary | +--------+--------+--------------+-------------------------------------------+ | 67073 | 21 | EventLogging | Fix per schema counts in graphite | | | | | | | 67129 | 8 | Refinery | Admin has versioned and sync'ed files in | | | | | HDFS | | 67128 | 5 | Refinery | Admin has duplicate monitoring in Icinga | | | | | | | 65946 | 13 | Wikimetrics | Story: CronUser runs EEVS metrics on all | | | | | projects daily | | 66841 | 8 | Wikimetrics | Story: CronUser backfills NewlyRegistered | | | | | User for recurring reports | | 66087 | 3 | Wikimetrics | Path to recurrent report (from dashboard) | | | | | should have better semantics | +--------+--------+--------------+-------------------------------------------+
Points Total: 58
Points per Component: 21 EventLogging 13 Refinery 24 Wikimetrics
Have fun, Christian
Hi,
On Wed, Jul 02, 2014 at 11:00:44AM +0200, Christian Aistleitner wrote:
On Tue, Jul 01, 2014 at 09:16:26AM -0700, Kevin Leduc wrote:
Our current sprint started Thursday June 26 and ends Tuesday July 8th. [...] http://sb.wmflabs.org/t/analytics-developers/2014-06-26/
Of the originally planned 58 points, we delivered 45 points.
We did not accomplish:
| 67129 | 8 | Refinery | Admin has versioned and sync'ed files in | | | | | HDFS | | 67128 | 5 | Refinery | Admin has duplicate monitoring in Icinga |
Both items have been carried over to the new sprint. * Bug 67129 has been done in the meantime. * Bug 67128 has been re-discussed and had it's requirements and purpose changed considerably, and now better fits the overall picture and delivers more value. But it also made the card bigger.
Have fun, Christian
Just out of curiosity (as a product owner myself), as I can see the team is planning and delivering more and more at each sprint 16, 31, 45 and 55 (current sprint): is there any reason for such increase in velocity ?
Oh btw kudos for all the features delivered, and thank you for the transparency which is not always easy to do :)
2014-07-16 0:17 GMT+02:00 Christian Aistleitner christian@quelltextlich.at :
Hi,
On Wed, Jul 02, 2014 at 11:00:44AM +0200, Christian Aistleitner wrote:
On Tue, Jul 01, 2014 at 09:16:26AM -0700, Kevin Leduc wrote:
Our current sprint started Thursday June 26 and ends Tuesday July 8th. [...] http://sb.wmflabs.org/t/analytics-developers/2014-06-26/
Of the originally planned 58 points, we delivered 45 points.
We did not accomplish:
| 67129 | 8 | Refinery | Admin has versioned and sync'ed
files in |
| | | | HDFS
|
| 67128 | 5 | Refinery | Admin has duplicate monitoring in
Icinga |
Both items have been carried over to the new sprint.
- Bug 67129 has been done in the meantime.
- Bug 67128 has been re-discussed and had it's requirements and purpose changed considerably, and now better fits the overall picture and delivers more value. But it also made the card bigger.
Have fun, Christian
-- ---- quelltextlich e.U. ---- \ ---- Christian Aistleitner ---- Companies' registry: 360296y in Linz Christian Aistleitner Kefermarkterstrasze 6a/3 Email: christian@quelltextlich.at 4293 Gutau, Austria Phone: +43 7946 / 20 5 81 Fax: +43 7946 / 20 5 81 Homepage: http://quelltextlich.at/
Analytics mailing list Analytics@lists.wikimedia.org https://lists.wikimedia.org/mailman/listinfo/analytics
Hi Pierre-Selim
Before the last sprint, we adjusted how many points we assign to stories. We didn't have enough range to compare the complexity, and all things ended up being 5, 8 or 13 points. This was identified at a retrospective so we decided to recalibrate our points scale. Therefore it's not useful to compare the points in the last sprint with the past. We mentioned this during our last showcase.
https://docs.google.com/a/wikimedia.org/presentation/d/1Y2uI_oOhXGpcn8y-EHBA...
And yes, over the last few months our velocity has been increasing. I think there are many reasons for this: - we have not added or lost any new team members in the last 3 months - as the new product manager, I have been creating smaller stories and helping the team focus (I'm trying hard not to take all the credit here) - the team has really taken on completing its commitments during a sprint and we have been very interested where we are at at each scrum (we use a spreadsheet and burn up hours) - We have also been focused on fewer quarterly goals have pushed back on some issues/requests.
On Tue, Jul 15, 2014 at 3:27 PM, Pierre-Selim pierre-selim@huard.info wrote:
Just out of curiosity (as a product owner myself), as I can see the team is planning and delivering more and more at each sprint 16, 31, 45 and 55 (current sprint): is there any reason for such increase in velocity ?
Oh btw kudos for all the features delivered, and thank you for the transparency which is not always easy to do :)
2014-07-16 0:17 GMT+02:00 Christian Aistleitner < christian@quelltextlich.at>:
Hi,
On Wed, Jul 02, 2014 at 11:00:44AM +0200, Christian Aistleitner wrote:
On Tue, Jul 01, 2014 at 09:16:26AM -0700, Kevin Leduc wrote:
Our current sprint started Thursday June 26 and ends Tuesday July 8th. [...] http://sb.wmflabs.org/t/analytics-developers/2014-06-26/
Of the originally planned 58 points, we delivered 45 points.
We did not accomplish:
| 67129 | 8 | Refinery | Admin has versioned and sync'ed
files in |
| | | | HDFS
|
| 67128 | 5 | Refinery | Admin has duplicate monitoring in
Icinga |
Both items have been carried over to the new sprint.
- Bug 67129 has been done in the meantime.
- Bug 67128 has been re-discussed and had it's requirements and purpose changed considerably, and now better fits the overall picture and delivers more value. But it also made the card bigger.
Have fun, Christian
-- ---- quelltextlich e.U. ---- \ ---- Christian Aistleitner ---- Companies' registry: 360296y in Linz Christian Aistleitner Kefermarkterstrasze 6a/3 Email: christian@quelltextlich.at 4293 Gutau, Austria Phone: +43 7946 / 20 5 81 Fax: +43 7946 / 20 5 81 Homepage: http://quelltextlich.at/
Analytics mailing list Analytics@lists.wikimedia.org https://lists.wikimedia.org/mailman/listinfo/analytics
-- Pierre-Selim
Analytics mailing list Analytics@lists.wikimedia.org https://lists.wikimedia.org/mailman/listinfo/analytics