On Wed, Aug 3, 2011 at 2:54 AM, Rob Lanphier <robla(a)wikimedia.org> wrote:
* 482 revs for code review. September 16 completion?
Given your data-based approach, that sounds good to me. Also consider
that het deploy will be 'done' at some point and Aaron will have more
time to spend on review. Besides that, I will have fewer meetings once
I start working from home again, and Tim will get back in mid-August
(he's been out for most of the period you're analyzing).
* Question: do we have to wait until code review is
done before
deploying to test2?
YES. It runs on the production servers. We may relax our
standards a
little bit (e.g. we don't really need fixme resolution for
not-very-critical issues that aren't related to security or
performance), but everything still has to at least have been reviewed
for security and other do-we-dare-run-this-on-the-cluster issues.
* Question: could Roan, Tim, Brion and others in
Haifa get together
and decide a reasonable target date for deployment? (probably late
September sometime)
Sure.
Roan